No rule fires for this kit in Minneapolis in December. The result is waiting for manual review before we call it a pass.

The kit contains 1 × EcoFlow DELTA 3 Plus and 1 × EcoFlow 220W Bifacial Portable Solar Panel (EF-Fold-G220-04). The maker does not publish how the panels are wired, so we check the layout a 12 V controller can start on with the fewest panels in series: 1 in series × 1 strings.

Open this kit in the checker

What fails, and where

In all three: Phoenix (warm, December), Denver (moderate, December) and Minneapolis (cold, December): 33 of 34 pass

A year with this kit in three climates

Across the nine runs the same kit goes from no blackouts (van in Phoenix) to 365 days without power (cabin in Phoenix). The hardware is identical in every run. Only the weather and the load change, so a review from one location says little about yours.

Hour-by-hour simulation on NREL typical weather years; the load is the same every day; no vehicle or shore charging.
UsePhoenix, AZ (warm)Denver, CO (moderate)Minneapolis, MN (cold)
VanWeekend van, 400 Wh a dayno blackouts21 days without powerfirst 5 Jan, longest 4 days116 days without powerfirst 3 Jan, longest 44 days
CabinYear-round cabin, 1,697 Wh a day365 days without powerfirst 1 Jan, longest 365 days365 days without powerfirst 1 Jan, longest 365 days365 days without powerfirst 1 Jan, longest 365 days
GarageGarage backup, 453 Wh a dayno blackouts8 days without powerfirst 5 Jan, longest 3 days95 days without powerfirst 3 Jan, longest 25 days

What to add so it passes in the cold

As an Amazon Associate and through direct retailer programs, this site earns from qualifying purchases — see how.

Computed from the circuit at the cold location with 0.5 m, 1.5 m and 4 m cable runs. Prices are not tracked yet; the buy column is an Amazon search for the named part, not a specific listing we have checked (no direct manufacturer program joined yet, §13.3).
PartWhyQtyBuy
Cable 10 , 8.8 mpanels to controller, red + black, 4 m run12.4 A × 1.56 = 19.3 A; 1.7 % drop at 18.4 V string voltage.8.8 mSearch
Adapter MC4 to XT60The panel and station connectors differ.1Search

How this page was computed

Every compatibility rule the checker has runs against the kit in the worst solar month of each city. The year is simulated hour by hour with the listed loads; parts to add come from the auto-fix and the computed parts list.

The formulas are the same open engine the checker runs; the methodology page lists every constant.

These results are for reference. Wiring must be installed by a qualified electrician. Mobile installations follow ABYC E-11; stationary ones NEC 690/706.